Toshiba Energy Systems and Solutions Corporation announced that its Australian subsidiary, Toshiba International Corporation, has got a major contract to retrofit steam turbines, generators, and associated equipment as part of the modernization project of EnergyAustralia’s Mt Piper Power Station in Portland, Australia a subsidiary of Hong Kong-based China Light and Power.

Article continues below




The overall retrofit work is scheduled to be completed by the end of 2021.

The first unit of the Mt Piper Power Station started commercial operation in 1992 and the second unit started in 1993.

The steam turbines, generators and associated equipment were supplied by Toshiba ESS for both units.

These units can generate enough energy to meet around 15 per cent of New South Wales energy demand.

The project will increase Mt Piper’s output from 1400MW to 1460MW of critical base load generation that is equivalent to the needs of 55,000 homes without any increase in coal consumption or emissions.

The increase in output will be achieved through the replacement/upgrade of major equipment including steam turbine, generator and heat exchangers.

TIC won the order on the strength of Toshiba ESS’s world leading high efficiency steam path design, local service capabilities and proven results providing major thermal upgrades globally.


What to read next

U.S. judge postpones decision in bid to block Toshiba memory unit sale
Toshiba to sell medical unit to Canon for $6.1 billion
Toshiba to enter British nuclear power consortium